Project Overview
Intrepid Civil and Marine was engaged by Aecon Group Inc. to deliver specialist piling and marine construction works for the St Vincent Port Modernisation Project. The subcontract scope included offshore geotechnical investigations, installation and protection of a new offshore sewer pipeline, and installation of a combi wall marine retaining structure with a tied-back anchor system.

Key Scope of Works
Offshore Geotechnical Investigations
Borehole drilling and geotechnical sampling. offshore using Intrepid’s jack-up barge with B60 drill rig
Offshore Sewer Pipeline Installation
Installation of a new 400 mm diameter HDPE welded sewer pipeline along a new offshore alignment (1,000m long, to a max depth –35 m)